Swimming Pool Structural Works

Swimming Pool Structural Works

Time to complete

2 weeks

Budget

£71,000

Works included:

  • Installation of new structural steel work in the undercroft to support the existing swimming pool
  • Structural splicing to ensure the steel work fitted through the tight access hatches
  • Removal and reinstallation of electrical services including lighting and power
  • Relocating 4 existing gullies including laying new tiles
  • Installation of new access hatch
  • Decorating existing ‘A’ frames in chlorine resistant paint to reduce long term corrosion

GB Contract Services were successful in tendering for the design and build of the structural repairs to the steel work for the swimming pool at Haileybury and Imperial Service College.

Works were carried in during half term with a strict deadline of 2 weeks which we managed to achieve.