NW Quad Underpinning

NW Quad Underpinning

Time to complete

8 weeks

Budget

£210,000

Works included:

  • Excavation of area to allow for piling
  • Screw piles to the necessary depth
  • Installation of new steels to support existing structure
  • Installation of new concrete to protect new steels
  • Installation of new helibar over the extensive cracking
  • Making good of brickwork including ensuring any repairs were in keeping to the original build due to the building being listed
  • Plastering the internal room to make it good
  • Decorations to the internal room
  • Making good of driveway

GB Contract Services were successful in tendering for the design and build of structural underpinning works at Haileybury & Imperial Service College.
Working with our existing supply chain GB Contract Services produced design drawings compliant to building regulations. This project required careful consideration as the building was listed.